The challenge
UAE Consulate in Toronto had milestones that existed on a public timetable rather than a construction one. Missing a reporting date was as serious as missing a trade.
That makes the chasing critical. Most of a schedule slipping is a question nobody followed up.
What we did
Every open question had an owner and a date by which it became a delay, and was asked again before that date rather than after it.
The budget was reported as committed against approved rather than spent against budget, which is the version that lets somebody act while there is still time.
The outcome
UAE Consulate met its reporting obligations on time, with the schedule and the record telling the same story on the same day.
More case studies
Case studyThree Months, $1.5 Million, and 60+ Change Orders: Transforming Embassy Grand Banquet Hall
Embassy Grand needed its entrance floors and bathrooms rebuilt in three months. See how 60+ change orders landed without moving the date or losing an event.
Case studyCustomizing Spaces: Delivering Four Unique Tenant Buildouts in a Health and Medical Building
Four tenants, four fit-outs, one new medical building, six months. See how WeReno Capital ran the permits, design and trades so every tenant moved in on time.
Case studyRevitalizing Turtle Jacks: A Flooring Makeover Without Closing
Turtle Jacks needed new flooring in a restaurant that never stops serving. See how pre-cut, dust-free installation ran on slow days with the doors still open.Tell us what you are running.
Capital is on live projects now and the three agents are in early access. Tell us about the job and a representative will be in touch shortly.