The challenge
Travelodge in Edmonton had the usual split: a capital improvement plan on one side and day-to-day maintenance on the other, both wanting the same rooms and the same trades.
Run separately they collide. A room taken for maintenance is a room the improvement plan cannot have, and neither side sees the other’s schedule.
What we did
WeReno ran both from one schedule, so a room came out of service once and went back finished. Preventative work was timed to the improvement sequence rather than to a separate calendar.
Everything was recorded against the property: what was done, by whom, what it cost and what is due next.
The outcome
Travelodge kept more rooms sellable across the programme, and finished it with a maintenance record that carried forward rather than ending with the project.
More case studies
Case studyThree Months, $1.5 Million, and 60+ Change Orders: Transforming Embassy Grand Banquet Hall
Embassy Grand needed its entrance floors and bathrooms rebuilt in three months. See how 60+ change orders landed without moving the date or losing an event.
Case studyCustomizing Spaces: Delivering Four Unique Tenant Buildouts in a Health and Medical Building
Four tenants, four fit-outs, one new medical building, six months. See how WeReno Capital ran the permits, design and trades so every tenant moved in on time.
Case studyRevitalizing Turtle Jacks: A Flooring Makeover Without Closing
Turtle Jacks needed new flooring in a restaurant that never stops serving. See how pre-cut, dust-free installation ran on slow days with the doors still open.Tell us what you are running.