The challenge
Refreshing Holiday Inn (Celebration) in Orlando meant working in a building full of paying guests. Corridors, lifts and public areas all had to stay usable, clean and quiet enough to sell.
The schedule was the constraint that mattered. Every week a floor stayed down was a week of rooms nobody could book.
How we ran it
One record held the scope, the procurement schedule and the approvals, so the owner and the operator were reading the same file rather than trading updates.
We chased the questions that stall a hotel programme — the supplier confirmations, the inspection bookings — before they turned into an idle crew and an empty floor.
The outcome
The refresh at Holiday Inn (Celebration) landed inside its window with the property trading throughout, and the final account reconciled line by line against the award.
More case studies
Case studyThree Months, $1.5 Million, and 60+ Change Orders: Transforming Embassy Grand Banquet Hall
Embassy Grand needed its entrance floors and bathrooms rebuilt in three months. See how 60+ change orders landed without moving the date or losing an event.
Case studyCustomizing Spaces: Delivering Four Unique Tenant Buildouts in a Health and Medical Building
Four tenants, four fit-outs, one new medical building, six months. See how WeReno Capital ran the permits, design and trades so every tenant moved in on time.
Case studyRevitalizing Turtle Jacks: A Flooring Makeover Without Closing
Turtle Jacks needed new flooring in a restaurant that never stops serving. See how pre-cut, dust-free installation ran on slow days with the doors still open.Tell us what you are running.
Capital is on live projects now and the three agents are in early access. Tell us about the job and a representative will be in touch shortly.