The challenge
Holiday Inn Express & Suites in Halifax had a property improvement plan to meet and no appetite for closing to do it. Rooms out of service are rooms not sold, so the number of floors down at once was a revenue decision before it was a construction one.
Brand standards also leave little room for interpretation. The specification is the specification, and an inspection at the end is not the moment to discover a substitution.
What we did
WeReno ran the plan floor by floor, with a fixed number of rooms out of service at any time and a sequence that kept noisy work away from occupied floors.
Materials were confirmed against the brand standard before they were ordered, and the long-lead items were on site before the floor they belonged to came down.
The outcome
Holiday Inn Express & Suites met the standard without an unplanned closure, and the owner had a record of every substitution, approval and cost as the work ran rather than after it.
More case studies
Case studyThree Months, $1.5 Million, and 60+ Change Orders: Transforming Embassy Grand Banquet Hall
Embassy Grand needed its entrance floors and bathrooms rebuilt in three months. See how 60+ change orders landed without moving the date or losing an event.
Case studyCustomizing Spaces: Delivering Four Unique Tenant Buildouts in a Health and Medical Building
Four tenants, four fit-outs, one new medical building, six months. See how WeReno Capital ran the permits, design and trades so every tenant moved in on time.
Case studyRevitalizing Turtle Jacks: A Flooring Makeover Without Closing
Turtle Jacks needed new flooring in a restaurant that never stops serving. See how pre-cut, dust-free installation ran on slow days with the doors still open.Tell us what you are running.
Capital is on live projects now and the three agents are in early access. Tell us about the job and a representative will be in touch shortly.