The challenge
The Garrison Bespoke showcase had an opening date set by a campaign, not by a construction schedule. The floor was trading, the access windows were narrow, and the finish had to meet a brand standard on the day it was revealed.
There is no version of this where the date moves. Everything else bends around it.
What we did
We built the programme backwards from the reveal, with fabrication and delivery timed to the access windows the store could actually give us.
Install happened outside trading hours, and the space was returned to a sellable state at the end of every shift rather than at the end of the job.
The outcome
The Garrison Bespoke showcase opened on its date, to the brand’s specification, without the floor losing a day of trade.
More case studies
Case studyThree Months, $1.5 Million, and 60+ Change Orders: Transforming Embassy Grand Banquet Hall
Embassy Grand needed its entrance floors and bathrooms rebuilt in three months. See how 60+ change orders landed without moving the date or losing an event.
Case studyCustomizing Spaces: Delivering Four Unique Tenant Buildouts in a Health and Medical Building
Four tenants, four fit-outs, one new medical building, six months. See how WeReno Capital ran the permits, design and trades so every tenant moved in on time.
Case studyRevitalizing Turtle Jacks: A Flooring Makeover Without Closing
Turtle Jacks needed new flooring in a restaurant that never stops serving. See how pre-cut, dust-free installation ran on slow days with the doors still open.Tell us what you are running.
Capital is on live projects now and the three agents are in early access. Tell us about the job and a representative will be in touch shortly.