The challenge
Hampton Inn needed a property improvement plan to modernize and meet new corporate standards. Updating five floors posed a challenge, as the project had to be completed in phases without disrupting hotel services or guest experiences.
Objective
The goal was to upgrade bathrooms, tv, blinds, curtains, and flooring without disrupting daily operations or inconveniencing guests. The entire process required thorough documentation to keep corporate informed of the project’s progress and results.
The strategy
To meet these goals, we implemented a detailed strategy to ensure clarity and efficiency throughout the project.
Design Process
To ensure that the project aligned with the client’s vision, we worked closely with an interior designer. This collaboration helped us capture the aesthetic and functional goals of the property improvement plan while staying within the client’s budget. The focus was on achieving a cohesive look that aligned with Hampton Inn’s corporate standards while maximizing value for the hotel.
Dashboard
We centralized floor layouts and room measurements on a single dashboard, ensuring precise documentation and clear updates to corporate on project progress. The dashboard also tracked contractors, simplifying reference for warranty work or future needs. This method streamlined the renovation process and maintained transparency throughout.
Prioritization
In coordination with hotel management, we identified floor bookings and scheduled work during slower periods to minimize guest disruption. We aimed to complete each floor in seven days, offering complimentary upgrades to clear floors faster and accelerate the renovation. This proactive approach enabled efficient work and sometimes early completion.
WeReno was a game-changer for our project. The detailed quality assurance and round-the-clock support made a huge difference. It’s essential for managing complex projects with precision.
Owner
Hampton Inn
WeReno Capital ran this one. See how it runs a project like this.
Ready to build or renovate?
Tell us about the building and the date you need it open. We will tell you what we would put on it.
More case studies
Case studyThree Months, $1.5 Million, and 60+ Change Orders: Transforming Embassy Grand Banquet Hall
Embassy Grand needed its entrance floors and bathrooms rebuilt in three months. See how 60+ change orders landed without moving the date or losing an event.
Case studyCustomizing Spaces: Delivering Four Unique Tenant Buildouts in a Health and Medical Building
Four tenants, four fit-outs, one new medical building, six months. See how WeReno Capital ran the permits, design and trades so every tenant moved in on time.
Case studyRevitalizing Turtle Jacks: A Flooring Makeover Without Closing
Turtle Jacks needed new flooring in a restaurant that never stops serving. See how pre-cut, dust-free installation ran on slow days with the doors still open.Tell us what you are running.
Capital is on live projects now and the three agents are in early access. Tell us about the job and a representative will be in touch shortly.